Question

Consider the basic COCOMO model where EE is the effort applied in person-months, DD is the development time in chronological months, KLOC is the estimated number of delivered lines of code (in thousands) and ab,bb,cb,dba_b, b_b, c_b, d_b have their usual meanings. The basic COCOMO equations are of the form

Choose one option
Official answer and solution
Official answer
A
From
Official GATE 2015 answer key

Solution

Recall the standard empirical equations of Boehm's Basic COCOMO model.

In Barry Boehm's Basic COCOMO (Constructive Cost Model):

  1. Effort (EE) in person-months is given by a power law in the estimated size (KLOC):
E=ab(KLOC)bbE = a_b (\text{KLOC})^{b_b}

where aba_b and bbb_b are coefficients determined by the software project mode (organic, semidetached, embedded).

  1. Development Time (DD) in chronological months is given by a power law in the effort EE:
D=cb(E)dbD = c_b (E)^{d_b}

where cbc_b and dbd_b are mode-specific coefficients.

Thus, the basic COCOMO equations match option A.

Final answer

A

Common trap

Confusing the independent variable of development time DD, which depends on effort EE, not directly on KLOC.

The answer is the one in the official GATE answer key. The solution is this site's own explanation.

Source

Paper
GATE 2015 Computer Science and Information Technology (CS) Session 2
Question
22 of 65, printed as CS Q.12
Section
Computer Science and Information Technology

This question is from a part of the syllabus that is no longer in GATE CS. It is kept because it was in the paper.

Report an error in this question

GATE questions are the work of the organising institutes. This site is independent and is not affiliated with them.