Question
A company needs to develop digital signal processing software for one of its newest inventions. The software is expected to have 40000 lines of code. The company needs to determine the effort in person-months needed to develop this software using the basic COCOMO model. The multiplicative factor for this model is given as 2.8 for the software development on embedded systems, while the exponentiation factor is given as 1.20. What is the estimated effort in person-months?
Official answer and solution
- Official answer
- A
- From
- Official GATE 2011 answer key
Solution
Apply the basic COCOMO effort estimation formula using the given multiplicative and exponential parameters.
- The basic COCOMO effort equation is:
- Convert lines of code to thousands of lines of code:
- Substitute the given parameters and :
- Evaluating :
A
The answer is the one in the official GATE answer key. The solution is this site's own explanation.
Source
- Paper
- GATE 2011 Computer Science and Information Technology (CS)
- Question
- 7 of 65, printed as CS Q.7
- Section
- Computer Science and Information Technology