Question
A transporter receives the same number of orders each day. Currently, he has some pending orders (backlog) to be shipped. If he uses 7 trucks, then at the end of the 4th day he can clear all the orders. Alternatively, if he uses only 3 trucks, then all the orders are cleared at the end of the 10th day. What is the minimum number of trucks required so that there will be no pending order at the end of the 5th day?
Official answer and solution
- Official answer
- C
- From
- Official GATE 2011 answer key
Solution
Set up a system of linear equations involving initial backlog, daily incoming order rate, and truck daily clearance capacity.
- Let:
- be the initial pending orders (backlog).
- be the number of incoming orders received per day.
- be the clearance capacity of one truck per day.
- Formulate equations for the two given operational conditions:
- Using 7 trucks for 4 days:
- Using 3 trucks for 10 days:
- Subtract equation (1) from equation (2):
- Substitute back into equation (1) to express the backlog in terms of :
- Let be the number of trucks required to clear all orders by the end of day 5.
The total orders to be shipped over 5 days equal the initial backlog plus 5 days of incoming orders:
In 5 days, trucks can ship:
To ensure there are no pending orders remaining:
- Since the number of trucks must be an integer, the minimum number of trucks required is .
C
The answer is the one in the official GATE answer key. The solution is this site's own explanation.
Source
- Paper
- GATE 2011 Computer Science and Information Technology (CS)
- Question
- 64 of 65, printed as GA Q.64
- Section
- General Aptitude
Report an error in this question
GATE questions are the work of the organising institutes. This site is independent and is not affiliated with them.